Process & Planning Pillar Guide Published 2026-11-26 · By Pillar 22

Kitchen Remodel Timeline: From Design to Done

How long a kitchen remodel really takes in Palm Beach County—from initial measurement and 8–12 week cabinet lead times to final city inspection.

One of the biggest surprises for homeowners planning a West Palm Beach kitchen remodel is the difference between total project duration (often 14 to 22 weeks from design kickoff to final inspection) and active on-site construction (typically 6 to 10 weeks for a full remodel, or 3 to 5 days for cabinet refacing).

Why the gap? Because material lead times and Palm Beach County permitting run before demolition—which is a good thing. At Pillar 22 (CBC1268572 / CCC1337493), we never tear out your sink and range until cabinets are built and permits are in motion.

Phase-by-Phase Timeline in West Palm Beach

Phase 1: In-Home Measure, Scope & Selections (Weeks 1–3)

We inspect your electrical panel, plumbing drains, slab flatness, and load-bearing walls, then finalize appliance specs, cabinet elevations, stone choices, and an itemized written quote.

Phase 2: Cabinet Fabrication & Permitting (Weeks 4–13, Concurrent)

  • Semi-Custom Plywood Cabinets: Usually 8 to 12 weeks from order sign-off.
  • City / County Permits & Condo HOA Review: Building, plumbing, electrical, and mechanical permits in West Palm Beach typically take 2 to 6 weeks (longer if historic preservation review applies in Flamingo Park or El Cid). Running permit review while cabinets are in production keeps your calendar compact.

Phase 3: Dust Containment, Demo & Rough Trades (Weeks 14–16)

Once cabinets arrive at our local staging warehouse or acclimate indoors, we protect haul routes, set plastic containment barriers, and complete demolition. Plumbers, electricians, and framing carpenters update rough-ins and pass rough city inspections before drywall closes.

Phase 4: Drywall, Flooring & Cabinet Installation (Weeks 17–18)

Walls are floated and primed, porcelain tile (if running under cabinets) is set, and base and upper cabinets are leveled and scribed cleanly to walls.

Phase 5: Countertop Templating & Fabrication (Weeks 19–20)

Countertops can only be digitally templated after base cabinets are permanently anchored. Stone fabrication takes 7 to 14 days, during which trim carpentry and painting wrap up.

Phase 6: Stone Install, Backsplash, Appliances & Final Inspection (Weeks 21–22)

Quartz or granite slabs are installed, plumbing is reconnected the following day, backsplash tile is set and grouted, appliances are hooked up, and we complete our punch walkthrough and final building department inspection.

Explore Every Process & Planning Guide in This Cluster

Want a custom project calendar for your home? Request a walkthrough via our full kitchen remodel page or contact form.